Latest news and updates

Next phase of Emergency Department refurbishment now open

September 18th, 2025|Comments Off on Next phase of Emergency Department refurbishment now open

18 September 2025 Eight more modern patient bays are now open in the Emergency Department at Royal Shrewsbury Hospital (RSH) as part of ongoing refurbishment and redevelopment work.   This follows new, larger purpose-built [...]

One-year anniversary of construction at Royal Shrewsbury Hospital

August 6th, 2025|Comments Off on One-year anniversary of construction at Royal Shrewsbury Hospital

6 August 2025 Work on a multi-million pound four-storey expansion of healthcare facilities at Royal Shrewsbury Hospital (RSH) is on track to complete in 2028, as the one-year anniversary of construction approaches.  The landscape [...]

Deliveries to arrive on site to support construction of two new wards at Royal Shrewsbury Hospital

August 5th, 2025|Comments Off on Deliveries to arrive on site to support construction of two new wards at Royal Shrewsbury Hospital

5 August 2025 Please be aware that from Friday 8 August, we are expecting some large deliveries to Royal Shrewsbury Hospital (RSH) as part of construction and installation of two new wards. The first [...]

Cutting-edge construction: The role of robotics at Royal Shrewsbury Hospital

July 7th, 2025|Comments Off on Cutting-edge construction: The role of robotics at Royal Shrewsbury Hospital

7 July 2025 Construction work currently underway at Royal Shrewsbury Hospital is making the most of modern technology to ensure maximum efficiency and precision. Working with sub-contractors, JCS Interiors Ltd, Hospitals Transformation Programme (HTP) [...]

Construction progress at Royal Shrewsbury Hospital

July 1st, 2025|Comments Off on Construction progress at Royal Shrewsbury Hospital

26 June 2025 Construction of new health care facilities at Royal Shrewsbury Hospital is soon approaching one-year since building work started. Watch the drone footage to get a real sense of the size and [...]