Our journey
Our plans were consulted on in 2018, and as we further develop the detailed models of care we want to engage service users, staff and other stakeholders to help inform our work and deliver the best possible value for patients and our staff. To fully realise our plans, we need to open our new emergency services at the Royal Shrewsbury Hospital. Building work has started and we hope to open our new building in 2028. We will then be able to make these changes and improve care for everyone.
May - September 2018
Future Fit public consultation
August 2022
Strategic Outline Case approved nationally
January 2024
Outline Business Case approved nationally
January 2024
Full planning permission for new healthcare facilities granted
May 2024
Full Business Case approved nationally
June 2024
New planned care hub at Princess Royal Hospital opens – aligned to our new ways of working
July 2024
Royal Shrewsbury Hospital Outpatient’s entrance closes – marking the start of construction
March 2025
First phase of emergency department remodelling complete at RSH